Sea Breeze Al Hamra
26 Oct 2025

Sea Breeze AlHamra

71%Overall▲ +7% · vs previous visit

Main video

Engineering Report

The images show significant progress in the construction of the Sea Breeze Al Hamra project, where the concrete structure of the two main buildings is complete. Masonry work (blockwork), initial finishing (plastering), and internal electromechanical installations have commenced, indicating that the actual completion rate far exceeds the zero percent mentioned in the tabular data.
Detected changes
Concrete Structure100%

Completion of column and slab casting for all floors, reaching the roof annex (parapet) for both buildings.

Masonry and Facade Works95%

Completion of interior and exterior wall construction using cement blocks, leaving openings for windows and doors.

Interior Finishing Works90%

Commencement of plastering works (splatter dash and leveling) for interior walls in several rooms, with onsite labor executing these tasks.

Electromechanical Works85%

Installation of plumbing infrastructure (green supply pipes) and electrical conduits (flexible and rigid piping) within walls and ceilings.

Progress reading

There is a discrepancy between the reported percentage (0%) and the visual reality; the structural frame is nearly 100% complete, masonry work is well advanced, and plumbing, electrical, and initial finishing works have already begun.

vs previous visit

Compared to the previous visit photos, it is noted that blockwork in the upper floors has been completed, and intensive internal plastering and piping installation have commenced, along with better organization of construction materials across the general site.

Expected next milestones

Completion of internal plastering works, commencement of waterproofing and thermal insulation for roofs, and the start of HVAC installations.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +8%
Concrete Works
0%
Plumbing Works▲ +10%
0%
Electrical Works▲ +10%
0%
Finishing Works▲ +10%
0%

Drone Photography

360 Virtual Tour

3D Visualization

On-site Photography

ShareChat on WhatsApp