Engineering Report
Detected changes
Completion of column and slab casting for all floors, reaching the roof annex (parapet) for both buildings.
Completion of interior and exterior wall construction using cement blocks, leaving openings for windows and doors.
Commencement of plastering works (splatter dash and leveling) for interior walls in several rooms, with onsite labor executing these tasks.
Installation of plumbing infrastructure (green supply pipes) and electrical conduits (flexible and rigid piping) within walls and ceilings.
Progress reading
There is a discrepancy between the reported percentage (0%) and the visual reality; the structural frame is nearly 100% complete, masonry work is well advanced, and plumbing, electrical, and initial finishing works have already begun.
vs previous visit
Compared to the previous visit photos, it is noted that blockwork in the upper floors has been completed, and intensive internal plastering and piping installation have commenced, along with better organization of construction materials across the general site.
Expected next milestones
Completion of internal plastering works, commencement of waterproofing and thermal insulation for roofs, and the start of HVAC installations.