Engineering Report
Detected changes
Completion of casting for typical floor columns and ongoing carpentry and reinforcement work for upper floor slabs using concrete pumps.
Commencement of internal and external wall masonry using cement blocks on the ground and first floors.
Installation of PVC conduits within concrete slabs prior to casting and preparation of piping routes in the constructed walls.
Organization of the storage area with supplies of wooden blocks and construction materials, alongside ongoing metal shoring works.
Progress reading
The increase in the concrete completion rate (+50%) aligns with the intensive activity observed in casting multiple slabs. Furthermore, photos showing pipe installations within the slabs and masonry support the rise in plumbing and electrical completion percentages.
vs previous visit
Compared to the previous visit, the project has progressed from the initial foundations and columns stage to the casting of typical floor slabs and the commencement of masonry work, creating a significant visual difference in the scale of the existing structure.
Expected next milestones
Completion of casting the remaining upper floor slabs, intensification of masonry work on the middle floors, and the commencement of initial plastering works.