17 Oct 2026
Main video
Engineering Report
Detected changes
The concrete structure of the building is fully complete, with a concrete pump currently on-site for final or supplementary operations.
Construction of external and internal walls using concrete blocks has been completed for all visible floors.
Initial plumbing and electrical conduits are visible on the building's surface and within structural voids, reflecting progress in these phases.
Progress reading
The images align with the reported completion percentages; the concrete structure is shown as 100% complete, while the blockwork and preliminary finishing works are consistent with the recorded progress (25% for finishing, 22% for plumbing, and 15% for electrical).
vs previous visit
Compared to the previous site visit, the project has progressed from an incomplete concrete structure to a fully completed structural frame, with significant advancements in masonry work and utility installations.
Expected next milestones
Commencement of plastering works, HVAC installations, and the initiation of waterproofing and thermal insulation for the roof.