Al Hamra Corner
17 Oct 2026

17 Oct 2026

41%Overall▲ +25% · vs previous visit

Main video

Engineering Report

The building's concrete structure is fully complete, with significant progress made in masonry (blockwork), plumbing, electrical installations, and preliminary finishing works compared to the previous site visit.
Detected changes
Concrete Structure100%

The concrete structure of the building is fully complete, with a concrete pump currently on-site for final or supplementary operations.

Masonry Works95%

Construction of external and internal walls using concrete blocks has been completed for all visible floors.

Plumbing and Electrical Works85%

Initial plumbing and electrical conduits are visible on the building's surface and within structural voids, reflecting progress in these phases.

Progress reading

The images align with the reported completion percentages; the concrete structure is shown as 100% complete, while the blockwork and preliminary finishing works are consistent with the recorded progress (25% for finishing, 22% for plumbing, and 15% for electrical).

vs previous visit

Compared to the previous site visit, the project has progressed from an incomplete concrete structure to a fully completed structural frame, with significant advancements in masonry work and utility installations.

Expected next milestones

Commencement of plastering works, HVAC installations, and the initiation of waterproofing and thermal insulation for the roof.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +24%
Concrete Works▲ +60%
0%
Plumbing Works▲ +17%
0%
Electrical Works▲ +10%
0%
Finishing Works▲ +10%
0%