Al Hamra Corner
2 Jul 2026

2 Jul 2026

10%OverallFirst visit — no previous comparison.

Main video

Engineering Report

A site visit to the SEA BREEZE project was conducted on July 2, 2026, where current works are concentrated on the concrete structure phase of the ground floor. The site shows active carpentry and reinforced steel work for columns and concrete walls, with the ground floor slab (Slab on Grade) completed across extensive parts of the project.
Detected changes
Concrete Structure95%

Completion of blinding concrete, footings, and ground floor slab pouring. Work is currently underway on formwork and reinforcement for vertical columns and elevator/staircase walls.

General Site and Fencing90%

The site is enclosed with temporary hoarding and project identification signage. Surrounding roads have been leveled, and material storage areas have been prepared.

Masonry and Finishing Works100%

No masonry, internal, or external finishing works have been executed to date, as the project is still in the early structural stages.

Progress reading

Visual observations align with the reported concrete work completion rate (8%), as works are currently limited to structural elements below and above ground level for the ground floor only. The absence of visible plumbing or electrical installations is consistent with the zero-percent completion report for those specific items.

vs previous visit

No previous visit for comparison

Expected next milestones

Casting the ground floor columns, and commencing the carpentry and reinforcement work for the ground floor ceiling.

Progress

0%OverallAverage item progress
0/4 complete
Concrete Worksnew
0%
Plumbing Worksnew
0%
Electrical Worksnew
0%
Finishing Worksnew
0%