Al Hamra Corner
29 Jul 2026

29 Jul 2026

13%Overall▲ +3% · vs previous visit

Main video

Engineering Report

Significant progress was made on the project's concrete structure during July, with the completion of the ground floor roof slab casting and the commencement of reinforcement and formwork for the first-floor columns, alongside ongoing initial service installations.
Detected changes
Concrete Structure100%

Completion of the ground floor roof slab casting, with reinforcement steel for the first-floor columns visible and wooden formwork installed for some, alongside metal scaffolding supporting the slab.

Finishing Works85%

Commencement of masonry (blockwork) in limited sections of the ground floor, accounting for the 5% progress recorded in the finishing works category.

General Site95%

Organization of the work area, with reinforcement steel and timber stockpiled on the newly cast roof, and PVC pipes present for electrical and mechanical installations.

Progress reading

The photos align with the recorded increase in concrete works (+12%), showing the transition from the roof formwork stage in the previous visit to a cast slab and new floor columns. The start of masonry work is also visible, supporting the 5% progress in finishing works.

vs previous visit

Compared to the photos from the previous visit (18-23), the project was at the formwork stage for the ground floor ceiling, whereas current photos (1-17) show a completed ceiling and the clear commencement of first-floor columns and masonry work.

Expected next milestones

Casting the first-floor columns, starting the formwork for the first-floor ceiling, and intensifying masonry work on the ground floor.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +4%
Concrete Works▲ +12%
0%
Plumbing Works
0%
Electrical Works
0%
Finishing Works▲ +5%
0%