19 Aug 2026
Main video
Engineering Report
Detected changes
Completion of concrete pouring for the first-floor slabs and commencement of formwork and reinforcement for the second-floor columns, with the concrete pump currently operational.
Commencement of supplying and stacking cement blocks within the casted floors, and construction of some internal partitions and walls.
Organization of truck and equipment movement around the site, with the appearance of initial plumbing and electrical conduits (sleeves) within the concrete elements and masonry.
Progress reading
The photos align with the surge in concrete work from 20% to 40%, clearly showing the transition from slab pouring to the columns of the new floor. The images also support the 5% start in plumbing and electrical work through visible installations in ceilings and walls, and an increase in finishing works to 15% due to the progress of masonry.
vs previous visit
Compared to the previous site visit photos, the project has progressed from the first-floor ceiling casting stage to an advanced stage in the second-floor columns. Additionally, masonry (blockwork) was not visible during the previous visit, whereas it is now clearly evident in several areas.
Expected next milestones
Casting the second-floor columns, commencing the formwork for the second-floor ceiling, and continuing masonry work on the lower floors.