Sea Breeze Al Hamra
24 Nov 2025

Sea Breeze AlHamra

86%Overall▲ +12% · vs previous visit

Main video

Engineering Report

Significant progress has been observed in the interior finishing and exterior facade works of the project. The work has transitioned from the completed structural phase to the plastering, ceramic tiling, and initial electrical and mechanical installation stages, with external scaffolding still in place to complete the facade work.
Detected changes
Concrete Structure and Masonry Works100%

Completion of the structural frame for both buildings, including external and internal masonry wall construction, with plastering works commenced in selected areas.

Interior Finishes95%

Commencement of wall ceramic installation in bathrooms using plastic spacers, and execution of internal plastering for rooms and corridors.

Electrical and Mechanical Works90%

Installation of electrical conduits in ceilings and walls, mounting of switch boxes, and completion of air conditioning and drainage piping extensions.

Exterior Facades and General Site100%

Facades covered with safety netting and scaffolding for external plastering, while the adjacent area continues to be used for material storage and construction waste.

Progress reading

Although the officially recorded percentages indicate 0%, field photos confirm that the structural phase has been surpassed and actual work has begun on plumbing, electricity, and finishing (plastering and ceramics). This necessitates an update to the completion rates to reflect the visual reality.

vs previous visit

Compared to the previous visit photos, progress is evident in the internal plastering works and the commencement of ceramic installation, which was not previously visible. Additionally, an increase in the density of electromechanical installations within the units was noted.

Expected next milestones

Completion of internal and external plastering works, commencement of primer painting works, and following up on floor tile installation after finishing the underground plumbing extensions.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +13%
Concrete Works
0%
Plumbing Works▲ +10%
0%
Electrical Works▲ +25%
0%
Finishing Works▲ +15%
0%

Drone Photography

360 View

3D Model

On-site Photography