Sea Breeze AlHamra
Main video
Engineering Report
Detected changes
Completion of the structural frame for both buildings, including external and internal masonry wall construction, with plastering works commenced in selected areas.
Commencement of wall ceramic installation in bathrooms using plastic spacers, and execution of internal plastering for rooms and corridors.
Installation of electrical conduits in ceilings and walls, mounting of switch boxes, and completion of air conditioning and drainage piping extensions.
Facades covered with safety netting and scaffolding for external plastering, while the adjacent area continues to be used for material storage and construction waste.
Progress reading
Although the officially recorded percentages indicate 0%, field photos confirm that the structural phase has been surpassed and actual work has begun on plumbing, electricity, and finishing (plastering and ceramics). This necessitates an update to the completion rates to reflect the visual reality.
vs previous visit
Compared to the previous visit photos, progress is evident in the internal plastering works and the commencement of ceramic installation, which was not previously visible. Additionally, an increase in the density of electromechanical installations within the units was noted.
Expected next milestones
Completion of internal and external plastering works, commencement of primer painting works, and following up on floor tile installation after finishing the underground plumbing extensions.