Sea Breeze Al Hamra
6 Jan 2026

Sea Breeze AlHamra

96%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The images show significant progress in the interior and exterior finishing works of the Sea Breeze Al Hamra project. The concrete structure is fully completed, and plastering works and marble installation for the stairs have commenced, alongside the installation of internal electrical and plumbing systems.
Detected changes
Concrete Structure and General Site100%

Completion of the structural frame for both buildings, with external scaffolding and green safety netting still in place. The general site appears organized with construction material stockpiles on the ground floor.

Interior Finishing Works95%

Execution of internal wall plastering, installation of marble for staircases, and commencement of primer painting works in several rooms.

Plumbing and Electrical Works90%

Installation of suspended sewage pipes in ceilings, electrical wiring within walls (conduits and boxes), and application of waterproofing in roof areas.

Progress reading

Although the officially recorded percentage is 0%, the images visually confirm that the project has surpassed the structural skeleton stage and entered advanced finishing phases (plastering, marble, and utility installations), indicating a discrepancy between the administrative updates and the actual field progress.

vs previous visit

Compared to the previous visit, there is a noticeable intensification of work on interior finishes and roof insulation, while the external structure and overall site condition remain stable.

Expected next milestones

Completion of external facade works, commencement of floor tiling installation, and installation of lighting fixtures and sanitary ware.

Progress

0%OverallAverage item progress
3/4 completeavg ▲ +3%
Concrete Works
0%
Plumbing Works
0%
Electrical Works
0%
Finishing Works▲ +10%
0%

Drone Photography

360 Photography

3D Rendering