Sea Breeze AlHamra
Main video
Engineering Report
Detected changes
Completion of the structural frame for both buildings, with external scaffolding and green safety netting still in place. The general site appears organized with construction material stockpiles on the ground floor.
Execution of internal wall plastering, installation of marble for staircases, and commencement of primer painting works in several rooms.
Installation of suspended sewage pipes in ceilings, electrical wiring within walls (conduits and boxes), and application of waterproofing in roof areas.
Progress reading
Although the officially recorded percentage is 0%, the images visually confirm that the project has surpassed the structural skeleton stage and entered advanced finishing phases (plastering, marble, and utility installations), indicating a discrepancy between the administrative updates and the actual field progress.
vs previous visit
Compared to the previous visit, there is a noticeable intensification of work on interior finishes and roof insulation, while the external structure and overall site condition remain stable.
Expected next milestones
Completion of external facade works, commencement of floor tiling installation, and installation of lighting fixtures and sanitary ware.