Detected changes
Completion of exterior and interior wall construction using cement blocks, and completion of all slab and roof parapet pouring.
Commencement of internal plastering works (spatter dash and smooth plastering) in corridors and rooms across several floors.
Arrival and storage of elevator equipment crates (Fuji Japan) inside the building, with initial electrical conduits visible in the ceilings.
Ongoing presence of construction debris on the adjacent land, with the project's temporary fencing remaining in good condition.
Progress reading
Although official percentages indicate 0%, the photos clearly show the completion of the structural phase (skeleton and masonry) and the start of the plastering stage. This signifies that the project has effectively moved past the foundation phase and has begun the initial stages of finishing works.
vs previous visit
Compared to the previous visit photos, there is a noticeable progress in the cleanliness of the interior site, the commencement of plastering works, and the mobilization of elevator materials, whereas the previous focus was on completing the masonry works.
Expected next milestones
Completion of interior plastering works, commencement of plumbing and electrical piping installations, and the start of waterproofing for roofs and bathrooms.