Sea Breeze AlHamra
Engineering Report
Detected changes
Completion of concrete pouring for the two main buildings, with the structure reaching the roof level and construction materials staged in the adjacent yards.
Execution of interior wall plastering, installation of gypsum boards for suspended ceilings in select rooms, and commencement of electrical and mechanical rough-ins (HVAC ducting).
Ongoing exterior plastering and facade preparation, with buildings covered by safety netting and existing metal scaffolding.
Progress reading
Although the recorded data indicates 0% progress, visual evidence confirms that the concrete structure phase is largely complete (approaching 100%) and the project has effectively entered the finishing and services stage. This necessitates an update to the official completion percentages to reflect the actual status on-site.
vs previous visit
Compared to the photos from the previous visit (21-26), progress is noted in the internal plastering works and the emergence of suspended ceiling (gypsum) works that were not previously visible, in addition to an increased pace of work on the external facades.
Expected next milestones
Completion of internal painting works, installation of ceramics and flooring, and the commencement of removing external scaffolding following the completion of facade finishing.