Sea Breeze Al Hamra
24 May 2025

24 May 2025

1%Overall▲ +1% · vs previous visit

Engineering Report

Site works have commenced at the Sea Breeze Al Hamra project, with current activities focused on the concrete structure phase for the foundations. Observations include the pouring of reinforced concrete for footings and the raft foundation using concrete pumps, alongside ongoing formwork and steel reinforcement for the remaining foundation sections, and the delivery of cement blocks to the site.
Detected changes
Concrete Structure100%

Execution of reinforced concrete pouring for the raft/footings using two pumps, with reinforcement completed for large sections of the raft and column starters visible.

Masonry Works95%

Supply and stockpiling of large quantities of cement blocks on-site in preparation for masonry works following the stripping of footing formwork.

Site General Works and Logistics100%

Installation of the project's perimeter hoarding and signage, with concrete mixers and heavy machinery present, and a designated construction waste collection area in the adjacent plot.

Progress reading

Visual observations align with the 5% completion rate for concrete works, as the project is in the early foundation stages (continuous pouring of footings). No plumbing, electrical, or finishing works were observed, justifying the 0% completion rate for these items.

vs previous visit

No previous visit available for comparison; this report serves as the baseline.

Expected next milestones

Completion of concrete footing pouring, commencement of foundation waterproofing, and start of column necks and ground beams.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +1%
Concrete Works▲ +5%
0%
Plumbing Works
0%
Electrical Works
0%
Finishing Works
0%

Drone Shots

Ground Photography

3D Rendering

ShareChat on WhatsApp