24 May 2025
Engineering Report
Detected changes
Execution of reinforced concrete pouring for the raft/footings using two pumps, with reinforcement completed for large sections of the raft and column starters visible.
Supply and stockpiling of large quantities of cement blocks on-site in preparation for masonry works following the stripping of footing formwork.
Installation of the project's perimeter hoarding and signage, with concrete mixers and heavy machinery present, and a designated construction waste collection area in the adjacent plot.
Progress reading
Visual observations align with the 5% completion rate for concrete works, as the project is in the early foundation stages (continuous pouring of footings). No plumbing, electrical, or finishing works were observed, justifying the 0% completion rate for these items.
vs previous visit
No previous visit available for comparison; this report serves as the baseline.
Expected next milestones
Completion of concrete footing pouring, commencement of foundation waterproofing, and start of column necks and ground beams.