1 Jul 2025
Main video
Engineering Report
Detected changes
Completion of steel reinforcement and formwork for ground floor columns across extensive areas of the site, with some columns already cast and others being prepared with wooden shuttering and bracing.
Organization of the material storage area, continued presence of the temporary perimeter fencing featuring the project's visual identity, and a high density of labor across various work zones.
Progress reading
The visual evidence aligns with the recorded 2% increase in concrete works (from 8% to 10%), as the project has transitioned from the foundations/ground beams stage to the vertical columns of the ground floor, explaining the slight rise in the overall completion percentage.
vs previous visit
Compared to the photos from the previous visit, there is a clear progression showing the column reinforcement steel rising above ground level and the commencement of vertical formwork installation, whereas previous photos focused on foundation work and ground leveling.
Expected next milestones
Casting of ground floor columns, commencement of carpentry and reinforcement for the ground floor ceiling, and the start of initial plumbing and electrical rough-ins within the structure.