Sea Breeze AlHamra
Main video
Engineering Report
Detected changes
Completion of column and slab pouring for typical floors, with external scaffolding remaining in place to support subsequent works.
Continuation of wall construction using cement blocks across various floors, and preparation of door and elevator openings.
Commencement of internal plastering and installation of wall ceramics in bathrooms, with construction materials (mortar bags and tiles) present on-site.
Installation of electrical conduits in ceilings and walls, and preparation of water supply and drainage points.
Facades covered with green safety netting, and the adjacent area utilized for staging construction waste and materials.
Progress reading
Although the officially recorded completion rate is 0%, the site photos confirm that the project has significantly surpassed the structural framework stage and entered the initial finishing phase. The discrepancy between the recorded percentage and the visual reality may be due to pending approvals of bills of quantities or payment certificates.
vs previous visit
Comparing current photos with previous ones shows clear progress in internal masonry (blockwork) and the commencement of tiling works which were not present during the previous visit, in addition to an increased density of electrical ceiling installations.
Expected next milestones
Completion of internal plastering works, commencement of window and door frame installations, and ongoing waterproofing for wet areas.