Engineering Report
Detected changes
Completion of columns and slabs for typical floors; work is currently underway on the columns and parapet of the upper annex (roof).
Most exterior and interior walls are completed using cement blocks, with additional block stockpiles noted on the upper floors.
Commencement of orange electrical conduit installation in walls and ceilings, and the rough-in of drainage paths.
Start of spatter-dash and initial plastering works for some interior walls on the lower floors.
The site is enclosed by a temporary fence, with a designated area for construction waste collection and material storage.
Progress reading
Although the officially recorded percentage is 0%, the photos reflect an advanced engineering reality that significantly exceeds the structural skeleton stage, as infrastructure installations and initial finishing works have already commenced.
vs previous visit
Compared to the photos from the previous visit, we note the completion of the final roof slab casting and the commencement of masonry work on the upper floors, which previously consisted only of columns. Additionally, the project has transitioned from the pure concrete structural phase to the internal rough-in stage.
Expected next milestones
Completion of annex masonry work, commencement of external plastering, and completion of electromechanical system installations.