Sea Breeze 2
Main video
Engineering Report
Detected changes
Completion of most upper floor slabs and roof rooms, with the final columns for the upper annexes clearly visible.
Significant progress in the construction of exterior and interior walls using cement blocks, reaching the upper floors in most sectors.
Installation of PVC piping within walls and vertical shafts, supporting a 55% completion rate for plumbing works.
Organization of the staging area and presence of concrete pouring equipment (pumps and mixers) on-site, with ongoing surrounding earthwork leveling.
Progress reading
The site photos align with the technical reports, showing the increase in concrete work (from 75% to 90%) through the completion of the structural frames. Furthermore, the widespread progress in internal masonry work accounts for the rise in finishing and utility installation percentages.
vs previous visit
Compared to the photos from the previous visit (21-26), we observe the transition from the formwork and reinforcement stage for slabs to the masonry stage and the completion of pouring key structural elements, reflecting the 15% leap in concrete works.
Expected next milestones
Full completion of masonry works, commencement of internal plastering, and installation of metal frames for doors and windows.