Sea Breeze 2
17 Jun 2026

Sea Breeze 2

56%Overall▲ +11% · vs previous visit

Main video

Engineering Report

Significant progress has been made on the Sea Breeze 2 project, with overall completion reaching 56%. Work is currently focused on finalizing the concrete structure, which is nearly 90% complete, alongside the acceleration of masonry work and the commencement of initial MEP (plumbing and electrical) installations within the units.
Detected changes
Concrete Structure95%

Completion of most upper floor slabs and roof rooms, with the final columns for the upper annexes clearly visible.

Masonry Works90%

Significant progress in the construction of exterior and interior walls using cement blocks, reaching the upper floors in most sectors.

Plumbing and Electrical Works85%

Installation of PVC piping within walls and vertical shafts, supporting a 55% completion rate for plumbing works.

General Site90%

Organization of the staging area and presence of concrete pouring equipment (pumps and mixers) on-site, with ongoing surrounding earthwork leveling.

Progress reading

The site photos align with the technical reports, showing the increase in concrete work (from 75% to 90%) through the completion of the structural frames. Furthermore, the widespread progress in internal masonry work accounts for the rise in finishing and utility installation percentages.

vs previous visit

Compared to the photos from the previous visit (21-26), we observe the transition from the formwork and reinforcement stage for slabs to the masonry stage and the completion of pouring key structural elements, reflecting the 15% leap in concrete works.

Expected next milestones

Full completion of masonry works, commencement of internal plastering, and installation of metal frames for doors and windows.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +11%
Plumbing Works▲ +10%
0%
Electrical Works▲ +10%
0%
Finishing Works▲ +10%
0%
Concrete Works▲ +15%
0%