Sea Breeze 2
30 Mar 2026

Sea Breeze 2

4%OverallFirst visit — no previous comparison.

Main video

Engineering Report

The Sea Breeze 2 project site was visited on March 30, 2026. Current works are focused on the concrete skeleton phase, specifically the casting of the ground floor columns. The site is witnessing intensive activity in carpentry and reinforced steel works, with a concrete pump present on-site to complete the casting operations.
Detected changes
Concrete Structure100%

Execution of carpentry and reinforcement for vertical columns, with the actual commencement of concrete pouring using a mobile pump for several columns.

Carpentry and Reinforcement Works95%

Workers continue preparing wooden formwork and strengthening it using metal jacks and timber panels to ensure column alignment during pouring.

General Site100%

Presence of heavy equipment (concrete pump) and distribution of construction materials, including timber and rebar, throughout the site.

Progress reading

Visual observations align with the reported concrete progress (despite being recorded as 0% in the input data, photos confirm the actual start of column casting). The 15% completion in plumbing works likely pertains to underground piping or preparations preceding the casting of structural elements.

vs previous visit

No previous visit available for comparison

Expected next milestones

Stripping column formwork, commencing carpentry and reinforcement for the ground floor ceiling, and completing the rough-in plumbing and electrical installations.

Progress

0%OverallAverage item progress
0/4 complete
Plumbing Worksnew
0%
Electrical Worksnew
0%
Finishing Worksnew
0%
Concrete Worksnew
0%