Sea Breeze 2
Main video
Engineering Report
Detected changes
Structural framework completed for most blocks, with ongoing internal partition masonry using cement bricks and closing of openings.
Execution of splash-coat (spraying) and commencement of internal plastering for some rooms and corridors, with construction materials (cement and sand bags) visible on-site.
Installation of PVC piping and conduits in bathrooms, along with the routing of orange electrical conduits in walls and ceilings.
External facades remain at the brick and concrete stage, while the general site shows organized construction materials with the temporary project fencing still in place.
Progress reading
The visual evidence aligns with the reported completion rates; the plastering and internal installations reflect the progress in plumbing (60%) and finishing (45%). The electrical work remains steady at 40%, as seen in the ongoing initial wiring without moving to the pulling or final installation stages.
vs previous visit
Compared to the June visit, there is a clear progress in closing architectural openings in the buildings, along with an increased intensity in internal plastering works and service installations (plumbing and electrical) that were incomplete in previous photos.
Expected next milestones
Completion of internal plastering works, commencement of waterproofing for bathrooms, and the start of preparing external facades for plastering or cladding works.