Sea Breeze 2
17 Oct 2026

Sea Breeze 2

65%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The project has seen continuous progress in finishing works and MEP systems, while maintaining the stability of the completed concrete structure. Work is proceeding steadily on-site, with the notable pace of completion maintained since the previous visit.
Detected changes
Concrete Structure100%

The concrete structure is 100% complete, with no new structural modifications.

Finishing Works and Systems85%

Interior and exterior finishing works are ongoing, with significant progress in plumbing and electrical installations within the residential units.

Progress reading

The images reflect a consistent 3% progress in plumbing, electrical, and finishing works, which aligns with the work pace observed on-site compared to the previous visit.

vs previous visit

Compared to the previous visit, there are no fundamental changes to the concrete structure; however, the images show an increase in work density inside the buildings, confirming the continued progress of finishing works and MEP systems.

Expected next milestones

Completion of interior finishing works, commencement of final electrical and plumbing fixture installations, and the start of site landscaping works.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +2%
Plumbing Works▲ +3%
0%
Electrical Works▲ +3%
0%
Finishing Works▲ +3%
0%
Concrete Works
0%