8 Nov 2026
Main video
Engineering Report
Detected changes
Concrete pouring for the foundations continues using a stationary pump, with on-site personnel leveling the surfaces.
Progress reading
The images align with a 3% increase in foundation completion, clearly showing continuous pouring operations. Additionally, the start of structural concrete work (5%) is evident through the preparation of several footings and columns that are beginning to take shape.
vs previous visit
Compared to the previous site visit, the project has progressed from the reinforcement and formwork preparation stage for the foundations to the actual concrete pouring phase, marking a significant qualitative advancement in the pace of work.
Expected next milestones
Completion of the entire foundation slab pouring, commencement of foundation waterproofing, and preparation for pouring the ground floor columns.