22%Overall▲ +2% · vs previous visit

Main video

Engineering Report

The current site visit confirms that foundation concrete pouring is ongoing, with intensive activity from concrete pumps observed, reflecting tangible progress in the project's infrastructure.
Detected changes
Foundations83%

Concrete pouring for the foundations continues using a stationary pump, with on-site personnel leveling the surfaces.

Progress reading

The images align with a 3% increase in foundation completion, clearly showing continuous pouring operations. Additionally, the start of structural concrete work (5%) is evident through the preparation of several footings and columns that are beginning to take shape.

vs previous visit

Compared to the previous site visit, the project has progressed from the reinforcement and formwork preparation stage for the foundations to the actual concrete pouring phase, marking a significant qualitative advancement in the pace of work.

Expected next milestones

Completion of the entire foundation slab pouring, commencement of foundation waterproofing, and preparation for pouring the ground floor columns.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +2%
Foundations▲ +3%
0%
Concrete Works▲ +5%
0%
Finishing Works
0%
Electromechanical
0%

Drone Photography

Ground Photography