Apex
17 Oct 2026

17 Oct 2026

6%Overall▲ +6% · vs previous visit

Main video

Engineering Report

The current site visit marks the commencement of construction activities, with a primary focus on foundation work. Notable progress has been observed in the preparation and insulation of concrete footings, alongside the initiation of concrete pouring in several sections.
Detected changes
Foundations95%

Site excavation and concrete footing preparation have been completed, including the application of bitumen waterproofing. Reinforced concrete pouring has commenced in sections of the site using concrete pumps.

Site Preparation90%

The site has been prepared for heavy machinery (concrete pumps, loaders), and equipment movement has begun to facilitate site leveling and pouring operations.

Progress reading

The overall completion rate of 6% reflects the transition from site preparation to active foundation work. The progress metrics (25% for foundations) align visually with the site status, which shows concrete footings already poured and prepared.

vs previous visit

Compared to the previous visit, the site has transitioned from a vacant plot to an active construction site featuring cast isolated concrete footings, with heavy machinery on-site for pouring operations.

Expected next milestones

Completion of the remaining concrete footings, commencement of column neck construction, and initiation of thermal and waterproofing works for the column necks.

Progress

0%OverallAverage item progress
0/4 complete
Foundationsnew
0%
Concrete Worksnew
0%
Finishing Worksnew
0%
Electromechanicalnew
0%