17 Oct 2026
Main video
Engineering Report
Detected changes
Site excavation and concrete footing preparation have been completed, including the application of bitumen waterproofing. Reinforced concrete pouring has commenced in sections of the site using concrete pumps.
The site has been prepared for heavy machinery (concrete pumps, loaders), and equipment movement has begun to facilitate site leveling and pouring operations.
Progress reading
The overall completion rate of 6% reflects the transition from site preparation to active foundation work. The progress metrics (25% for foundations) align visually with the site status, which shows concrete footings already poured and prepared.
vs previous visit
Compared to the previous visit, the site has transitioned from a vacant plot to an active construction site featuring cast isolated concrete footings, with heavy machinery on-site for pouring operations.
Expected next milestones
Completion of the remaining concrete footings, commencement of column neck construction, and initiation of thermal and waterproofing works for the column necks.