Sea Breeze Al Hamra
16 Jun 2025

16 Jun 2025

2%Overall▲ +1% · vs previous visit

Main video

Engineering Report

Significant progress has been observed in the structural framework of the Sea Breeze Al Hamra project. Work has transitioned from preliminary preparations to the pouring of concrete foundations and footings using central concrete pumps, while carpentry and reinforced steelwork continue across other sections of the site.
Detected changes
Concrete Structure100%

Commencement of reinforced concrete pouring for footings and foundations, along with the preparation of formwork and steel reinforcement for ground beams across multiple sectors.

Site Layout and Facilities95%

Heavy presence of pouring equipment (pumps and concrete mixers) on-site, with organized storage areas for materials and construction waste in the adjacent plot.

Signage and Fencing100%

Completion of the professional installation of the perimeter fencing, advertising billboards, and project identification signs.

Progress reading

The visual evidence aligns with the recorded increase in concrete works (from 5% to 8%). The transition from excavation and leveling to the actual pouring of the substructure is clearly visible, accounting for the 3% rise in progress.

vs previous visit

Compared to the previous visit, the site has progressed from reinforcement planning and preparation to the field pouring stage. Current images show concrete pumps actively in operation, whereas previous images were limited to preliminary carpentry and steel fixing works.

Expected next milestones

Completion of all ground footing pours, commencement of foundation waterproofing, and preparation for pouring column necks.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +1%
Concrete Works▲ +3%
0%
Plumbing Works
0%
Electrical Works
0%
Finishing Works
0%