16 Jun 2025
Main video
Engineering Report
Detected changes
Commencement of reinforced concrete pouring for footings and foundations, along with the preparation of formwork and steel reinforcement for ground beams across multiple sectors.
Heavy presence of pouring equipment (pumps and concrete mixers) on-site, with organized storage areas for materials and construction waste in the adjacent plot.
Completion of the professional installation of the perimeter fencing, advertising billboards, and project identification signs.
Progress reading
The visual evidence aligns with the recorded increase in concrete works (from 5% to 8%). The transition from excavation and leveling to the actual pouring of the substructure is clearly visible, accounting for the 3% rise in progress.
vs previous visit
Compared to the previous visit, the site has progressed from reinforcement planning and preparation to the field pouring stage. Current images show concrete pumps actively in operation, whereas previous images were limited to preliminary carpentry and steel fixing works.
Expected next milestones
Completion of all ground footing pours, commencement of foundation waterproofing, and preparation for pouring column necks.