Sea Breeze AlHamra
Main video
Engineering Report
Detected changes
Completion of the concrete structure for both buildings, including insulation and tiling for the roof, and the installation of some air conditioning units and mechanical equipment.
Execution of interior plastering and first-coat painting in corridors and rooms, along with the installation of suspended gypsum board ceilings in designated areas.
Installation of internal electrical wiring and distribution boxes, as well as marble washbasins and sewage piping in the bathrooms.
Facades are covered with safety netting and scaffolding for the completion of exterior plastering and painting; significant construction debris is noted in the area adjacent to the project.
Progress reading
Although the official recorded percentage is 0%, the photographs visually confirm that the project has surpassed the concrete structure stage and entered advanced phases of interior finishing (plastering, tiling, installations) and exterior facades. This indicates a discrepancy between the documented updates and the actual progress on-site.
vs previous visit
Compared to photos from the previous visit (such as photo 18), there is clear progress in roof insulation works; while the roofs were raw concrete in the previous visit, they are now covered with insulation layers and white tiling. Additionally, interior finishing works have advanced significantly.
Expected next milestones
Completion of final painting works, installation of lighting units and sanitary fixtures, removal of external scaffolding, and general site clearing of debris.