Sea Breeze Al Hamra
22 Jan 2026

Sea Breeze AlHamra

99%Overall▲ +3% · vs previous visit

Main video

Engineering Report

The project shows significant progress in interior and exterior finishing works. The concrete structure is fully completed, and plastering, primary painting, and ceramic tiling have commenced within the residential units, while external scaffolding remains in place for facade work.
Detected changes
Concrete Structure and Roofing100%

Completion of the concrete structure for both buildings, including insulation and tiling for the roof, and the installation of some air conditioning units and mechanical equipment.

Interior Finishes (Walls and Ceilings)95%

Execution of interior plastering and first-coat painting in corridors and rooms, along with the installation of suspended gypsum board ceilings in designated areas.

Plumbing and Electrical Works90%

Installation of internal electrical wiring and distribution boxes, as well as marble washbasins and sewage piping in the bathrooms.

Exterior Facades and General Site100%

Facades are covered with safety netting and scaffolding for the completion of exterior plastering and painting; significant construction debris is noted in the area adjacent to the project.

Progress reading

Although the official recorded percentage is 0%, the photographs visually confirm that the project has surpassed the concrete structure stage and entered advanced phases of interior finishing (plastering, tiling, installations) and exterior facades. This indicates a discrepancy between the documented updates and the actual progress on-site.

vs previous visit

Compared to photos from the previous visit (such as photo 18), there is clear progress in roof insulation works; while the roofs were raw concrete in the previous visit, they are now covered with insulation layers and white tiling. Additionally, interior finishing works have advanced significantly.

Expected next milestones

Completion of final painting works, installation of lighting units and sanitary fixtures, removal of external scaffolding, and general site clearing of debris.

Progress

0%OverallAverage item progress
3/4 completeavg ▲ +3%
Concrete Works
0%
Plumbing Works
0%
Electrical Works▲ +10%
0%
Finishing Works
0%