Sea Breeze Al Hamra
12 Aug 2025

12 Aug 2025

24%Overall▲ +10% · vs previous visit

Main video

Engineering Report

A site visit to the Sea Breeze Al Hamra project was conducted on August 12, 2025, showing an overall completion rate of 24%. Work is currently focused on the concrete skeleton phase, with masonry work commencing on the lower floors, alongside preliminary plumbing and electrical installations (first fix). The site is witnessing intensive construction activity, with concrete pouring equipment and material stockpiles present.
Detected changes
Concrete Structure100%

Completion of column and slab pouring for several floors, with ongoing formwork and reinforcement for the upper slabs. Images show the use of both metal and traditional timber formwork systems.

Masonry Works95%

Commencement of wall construction using concrete blocks on the ground and first floors, with visible stockpiles of blocks within the site.

Plumbing and Electrical Works85%

Installation of initial conduits within the concrete slabs prior to pouring, and the appearance of vertical piping in the shaft areas.

Site Logistics and General Layout100%

Presence of concrete pump trucks, timber stockpiles, and organized construction waste in an adjacent yard, with the completion of the project's temporary perimeter fencing.

Progress reading

Visual observations align with the reported completion rates; the 45% progress in concrete work is clearly evident in the completion of the lower floors' structure. The 15% finishing rate primarily reflects ongoing masonry work, while the plumbing and electrical percentages (25% and 10% respectively) reflect the rough-in works within the structural frame.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of the remaining ceiling casting, expansion of masonry work for the upper floors, and commencement of internal plastering for the floors with completed masonry.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +10%
Concrete Works▲ +15%
0%
Plumbing Works▲ +15%
0%
Electrical Works▲ +5%
0%
Finishing Works▲ +5%
0%

Drone Photography

Ground Photography

3D Rendering

ShareChat on WhatsApp