12 Aug 2025
Main video
Engineering Report
Detected changes
Completion of column and slab pouring for several floors, with ongoing formwork and reinforcement for the upper slabs. Images show the use of both metal and traditional timber formwork systems.
Commencement of wall construction using concrete blocks on the ground and first floors, with visible stockpiles of blocks within the site.
Installation of initial conduits within the concrete slabs prior to pouring, and the appearance of vertical piping in the shaft areas.
Presence of concrete pump trucks, timber stockpiles, and organized construction waste in an adjacent yard, with the completion of the project's temporary perimeter fencing.
Progress reading
Visual observations align with the reported completion rates; the 45% progress in concrete work is clearly evident in the completion of the lower floors' structure. The 15% finishing rate primarily reflects ongoing masonry work, while the plumbing and electrical percentages (25% and 10% respectively) reflect the rough-in works within the structural frame.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of the remaining ceiling casting, expansion of masonry work for the upper floors, and commencement of internal plastering for the floors with completed masonry.