16 Jul 2025
Engineering Report
Detected changes
Completion of pouring parts of the ground floor ceiling, with ongoing carpentry and reinforced steel work in other sections. Photos show the use of a concrete pump and ready-mix trucks on-site.
Installation of initial drainage and supply sleeves within the ground floor slabs prior to the pouring process.
Installation of the project's temporary perimeter fencing with identification signage, designation of a construction waste collection area, and organization of heavy equipment movement.
Progress reading
Visual observations align with the concrete completion rate (15%), as the project is still in the early structural stages (ground floor). Plumbing works (5%) are limited to embedded slab installations, while electrical and finishing works have not yet commenced, as confirmed by the photos which show an absence of electrical wiring, plastering, or masonry work.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of the entire ground floor roof slab casting, commencement of reinforcement and formwork for the first floor columns, and start of masonry works for the ground floor.