Sea Breeze Al Hamra
16 Jul 2025

16 Jul 2025

5%Overall▲ +2% · vs previous visit

Engineering Report

A field visit to the Sea Breeze Al Hamra project was conducted on July 16, 2025, showing an overall completion rate of 5%. Work is currently focused on the concrete structure of the ground floor, with ongoing reinforced concrete pouring for the slabs and preparation of reinforcement steel for the remaining sections, alongside the initial rough-in for plumbing works.
Detected changes
Concrete Structure100%

Completion of pouring parts of the ground floor ceiling, with ongoing carpentry and reinforced steel work in other sections. Photos show the use of a concrete pump and ready-mix trucks on-site.

Plumbing Works90%

Installation of initial drainage and supply sleeves within the ground floor slabs prior to the pouring process.

General Site100%

Installation of the project's temporary perimeter fencing with identification signage, designation of a construction waste collection area, and organization of heavy equipment movement.

Progress reading

Visual observations align with the concrete completion rate (15%), as the project is still in the early structural stages (ground floor). Plumbing works (5%) are limited to embedded slab installations, while electrical and finishing works have not yet commenced, as confirmed by the photos which show an absence of electrical wiring, plastering, or masonry work.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of the entire ground floor roof slab casting, commencement of reinforcement and formwork for the first floor columns, and start of masonry works for the ground floor.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +3%
Concrete Works▲ +5%
0%
Plumbing Works▲ +5%
0%
Electrical Works
0%
Finishing Works
0%