29 Jul 2025
Main video
Engineering Report
Detected changes
Concrete pouring operations for floor slabs using concrete pumps, and preparing wooden formwork for the remaining columns and ceilings.
Intensifying steel reinforcement work for slabs and beams, and organizing timber and construction materials on-site.
Installation of plumbing and electrical conduits (PVC) embedded within the floor slabs prior to the pouring process.
Organization of the material storage area and the presence of concrete mixer trucks and heavy equipment around the project perimeter.
Progress reading
The visual evidence aligns with the recorded increase in concrete works (+15%), clearly showing the transition from the preparation phase to the actual pouring of the slabs. Furthermore, images showing colored piping (orange and white) within the reinforcement support the reported completion percentages for plumbing and electrical works.
vs previous visit
Compared to the previous site visit photos, the project has progressed from the initial foundation and column stage to the pouring of extensive ceiling areas, with significant portions of the lower floors' structural framework completed and a noticeable increase in labor and equipment density.
Expected next milestones
Completing the pouring of the remaining ceiling sections, commencing masonry (blockwork) for the completed floors, and continuing the vertical service installations.