Sea Breeze Al Hamra
14 Sept 2025

Sea Breeze AlHamra

50%Overall▲ +12% · vs previous visit

Main video

Engineering Report

A site visit to the Sea Breeze Al Hamra project was conducted on September 14, 2025. It was observed that the concrete structure of the main buildings is complete, with significant progress in masonry work (blockwork) for facades and internal partitions, alongside the commencement of initial electrical and plumbing rough-ins.
Detected changes
Concrete Structure100%

Completion of column and slab casting for typical floors up to the roof annex, with elevator machine rooms and stairwells now visible.

Masonry Works95%

Advanced progress in cement blockwork for external facades and internal partitions, including curved walls and architectural openings for windows and doors.

Electrical and Plumbing Works85%

Commencement of wall chasing and installation of PVC piping and cable conduits, with MEP rough-in materials delivered to the site.

General Site Area90%

Installation of project branding and identity panels on the perimeter hoarding, with construction debris and raw materials present in the surrounding staging areas.

Progress reading

Although the officially recorded progress stands at 0%, visual inspection indicates substantial actual completion of the structural framework and masonry works. This necessitates an update to the progress percentages to accurately reflect the project's current status.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of internal plastering works, commencement of HVAC system installations, and initiation of rooftop waterproofing works.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +13%
Concrete Works▲ +30%
0%
Plumbing Works
0%
Electrical Works▲ +20%
0%
Finishing Works
0%