Engineering Report
Detected changes
Completion of column and slab casting for typical floors up to the roof annex, with elevator machine rooms and stairwells now visible.
Advanced progress in cement blockwork for external facades and internal partitions, including curved walls and architectural openings for windows and doors.
Commencement of wall chasing and installation of PVC piping and cable conduits, with MEP rough-in materials delivered to the site.
Installation of project branding and identity panels on the perimeter hoarding, with construction debris and raw materials present in the surrounding staging areas.
Progress reading
Although the officially recorded progress stands at 0%, visual inspection indicates substantial actual completion of the structural framework and masonry works. This necessitates an update to the progress percentages to accurately reflect the project's current status.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of internal plastering works, commencement of HVAC system installations, and initiation of rooftop waterproofing works.