26 Aug 2025
Main video
Engineering Report
Detected changes
Completion of column and slab pouring for the lower floors, with ongoing formwork and reinforcement for the upper floors. Photos show a concrete pump on-site during the pouring process.
Commencement of wall construction using cement blocks on the ground and first floors, with block materials staged within the structural frame.
Organization of the staging and equipment area, presence of concrete mixers on-site, and a designated construction waste area in the adjacent plot.
Progress reading
Visual observations align with the reported completion rates; the progress of the concrete structure (70%) reflects the buildings reaching the upper floors, while plumbing, electrical, and finishing works (20-40%) are evident through the start of masonry work and initial pipe installations visible in some structural openings.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of the remaining ceiling casting, expansion of masonry work for the upper floors, and commencement of internal plastering and basic utility installations.