Sea Breeze Al Hamra
26 Aug 2025

26 Aug 2025

38%Overall▲ +14% · vs previous visit

Main video

Engineering Report

The site visit for the Sea Breeze Al Hamra project was conducted on August 26, 2025, with an overall completion rate of 38%. Work is currently focused on the concrete structure phase, alongside the commencement of masonry and initial finishing works, with intensive concrete pouring activity observed in the upper sections of the buildings.
Detected changes
Concrete Structure100%

Completion of column and slab pouring for the lower floors, with ongoing formwork and reinforcement for the upper floors. Photos show a concrete pump on-site during the pouring process.

Masonry Works95%

Commencement of wall construction using cement blocks on the ground and first floors, with block materials staged within the structural frame.

Site Layout and Services90%

Organization of the staging and equipment area, presence of concrete mixers on-site, and a designated construction waste area in the adjacent plot.

Progress reading

Visual observations align with the reported completion rates; the progress of the concrete structure (70%) reflects the buildings reaching the upper floors, while plumbing, electrical, and finishing works (20-40%) are evident through the start of masonry work and initial pipe installations visible in some structural openings.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of the remaining ceiling casting, expansion of masonry work for the upper floors, and commencement of internal plastering and basic utility installations.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +14%
Concrete Works▲ +25%
0%
Plumbing Works▲ +15%
0%
Electrical Works▲ +10%
0%
Finishing Works▲ +5%
0%