Sea Breeze Al Hamra
23 Dec 2025

Sea Breeze AlHamra

94%Overall▲ +1% · vs previous visit

Main video

Engineering Report

The site visit revealed significant progress in the project's interior and exterior finishing works. Pouring of parts of the final floor roof has been completed, while plastering and floor/wall tiling continue within the residential units, alongside the installation of external metal and glass facades.
Detected changes
Concrete Structure95%

Completion of pouring parts of the upper roof slab and preparing structural openings and skylights.

Exterior Facades90%

Installation of longitudinal metal cladding and commencement of aluminum and glass section installation under green safety netting.

Interior Finishes95%

Execution of floor tiling and skirting, and installation of bathroom wall tiles, alongside ongoing plastering and primary painting (primer) works.

General Site85%

Continued presence of construction debris in the adjacent plot, with organization of the labor and material entry area.

Progress reading

Although the recorded percentages indicate 0%, the photographs visually confirm that the project has reached an advanced stage in the structural framework (largely complete) and has commenced the final finishing phase. This necessitates an update to the completion rates to reflect the actual status on the ground.

vs previous visit

Compared to photos from the previous visit, progress is noted in the concrete pouring of the upper roof (Image 4 vs. Image 22), along with an increased pace in interior finishing works and the installation of exterior facades.

Expected next milestones

Completion of roof waterproofing, completion of facade glass installation, and commencement of final electrical and plumbing installations (Final Fix).

Progress

0%OverallAverage item progress
2/4 completeavg ▲ +1%
Concrete Works
0%
Plumbing Works
0%
Electrical Works
0%
Finishing Works▲ +5%
0%

Drone Photography

360 Photography

3D Rendering

On-site Photography