Sea Breeze AlHamra
Main video
Engineering Report
Detected changes
Completion of pouring parts of the upper roof slab and preparing structural openings and skylights.
Installation of longitudinal metal cladding and commencement of aluminum and glass section installation under green safety netting.
Execution of floor tiling and skirting, and installation of bathroom wall tiles, alongside ongoing plastering and primary painting (primer) works.
Continued presence of construction debris in the adjacent plot, with organization of the labor and material entry area.
Progress reading
Although the recorded percentages indicate 0%, the photographs visually confirm that the project has reached an advanced stage in the structural framework (largely complete) and has commenced the final finishing phase. This necessitates an update to the completion rates to reflect the actual status on the ground.
vs previous visit
Compared to photos from the previous visit, progress is noted in the concrete pouring of the upper roof (Image 4 vs. Image 22), along with an increased pace in interior finishing works and the installation of exterior facades.
Expected next milestones
Completion of roof waterproofing, completion of facade glass installation, and commencement of final electrical and plumbing installations (Final Fix).