Sea Breeze 2
Main video
Engineering Report
Detected changes
Active concrete pouring for slabs and columns using concrete pumps, with completed formwork and reinforcement across large areas.
Installation of PVC drainage pipes and orange electrical conduits within the reinforcement mesh prior to pouring.
Cement brick walls appearing on lower floors to partition architectural spaces.
Heavy equipment presence (mixers, pumps) along with stockpiles of rebar and timber in the site yard.
Progress reading
The visual evidence aligns with the surge in concrete works from 0% to 20%, showing active pouring operations. Furthermore, images displaying in-slab conduits support the 20% completion in plumbing, while the start of masonry work accounts for the 5% progress in preliminary finishes.
vs previous visit
Compared to the previous visit, the site has progressed from the basic preparation stage to the intensive concrete structure pouring phase, as pumps and overhead formwork were not visible on this scale in the previous visit's photos.
Expected next milestones
Completing the pouring of the remaining slab areas, starting the removal of wooden formwork for the cast columns, and intensifying masonry work on the floors where the slabs have been poured.