Sea Breeze 2
11 Apr 2026

Sea Breeze 2

11%Overall▲ +7% · vs previous visit

Main video

Engineering Report

The Sea Breeze 2 project has seen significant progress in concrete structural works, with roof and column pouring currently underway using concrete pumps. Initial plumbing and electrical rough-ins have also commenced within the floor slabs, alongside ongoing carpentry and reinforced steel work across various areas of the site.
Detected changes
Concrete Structure100%

Active concrete pouring for slabs and columns using concrete pumps, with completed formwork and reinforcement across large areas.

Plumbing and Electrical Works95%

Installation of PVC drainage pipes and orange electrical conduits within the reinforcement mesh prior to pouring.

Masonry Works90%

Cement brick walls appearing on lower floors to partition architectural spaces.

General Site100%

Heavy equipment presence (mixers, pumps) along with stockpiles of rebar and timber in the site yard.

Progress reading

The visual evidence aligns with the surge in concrete works from 0% to 20%, showing active pouring operations. Furthermore, images displaying in-slab conduits support the 20% completion in plumbing, while the start of masonry work accounts for the 5% progress in preliminary finishes.

vs previous visit

Compared to the previous visit, the site has progressed from the basic preparation stage to the intensive concrete structure pouring phase, as pumps and overhead formwork were not visible on this scale in the previous visit's photos.

Expected next milestones

Completing the pouring of the remaining slab areas, starting the removal of wooden formwork for the cast columns, and intensifying masonry work on the floors where the slabs have been poured.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +8%
Plumbing Works▲ +5%
0%
Electrical Works
0%
Finishing Works▲ +5%
0%
Concrete Works▲ +20%
0%