Sea Breeze 2
Main video
Engineering Report
Detected changes
Completion of all structural elements and floor slabs, reaching 100% progress with most external scaffolding removed.
Completion of external and internal wall construction using cement blocks, with architectural openings prepared for windows and doors.
Commencement of internal wall plastering on multiple floors, with construction materials (cement bags) staged on-site.
Execution of waterproofing for floors in wet areas (bathrooms) and installation of primary drainage piping.
Progress reading
The increase in concrete works (from 90% to 100%) is clearly linked to the completion of the upper roof slabs visible in the aerial photography. Furthermore, the commencement of plastering and insulation explains the 4% increase in the finishing phase, while the images show ongoing electrical and plumbing installations within the walls without a significant change in overall percentages.
vs previous visit
Compared to the previous visit photos, it is noted that the structural framework of the front buildings has been completed, with a clear improvement in site cleanliness and the commencement of interior finishing stages that were not previously visible.
Expected next milestones
Commencement of window and door frame installation, completion of interior plastering works, and the start of mechanical, electrical, and plumbing (MEP) installations for the advanced stages.