Sea Breeze 2
Main video
Engineering Report
Detected changes
Ongoing formwork and metal shoring for slabs, along with the pouring of columns and stairs at various levels.
Execution of internal partition walls using concrete blocks, with additional materials delivered to the site.
Installation of initial PVC piping and wiring conduits within the slabs and walls.
Organization of construction materials and presence of pouring equipment (pumps and mixers) around the building perimeter.
Progress reading
The photographs align with the reported completion rates; the progress of concrete works (75%) is evident in the completion of most of the structural frame. Meanwhile, interior photos reflect the start of plumbing and electrical works (45% and 30% respectively) through visible installations in unplastered walls, as well as the commencement of preliminary finishing works (masonry).
vs previous visit
Compared to the previous visit, a larger area of internal walls has been closed with masonry, more concrete slabs have been poured, and formwork activities have progressed to higher levels of the structure.
Expected next milestones
Completion of the remaining slab pouring, commencement of internal plastering works, and intensification of electromechanical system installations.