19 Nov 2026
Main video
Engineering Report
Detected changes
Completed the pouring of the concrete roof slab and prepared the wooden and steel formwork for the preceding stages.
Installed electrical and mechanical conduits (supply and drainage pipes) within the reinforcement steel prior to the pouring process.
Progress reading
The photos align with the updated progress reports, reflecting the ongoing pouring operations that have increased concrete completion to 10%, and the commencement of MEP installations at 2%.
vs previous visit
Compared to the previous visit, the site has progressed from the preparation and reinforcement phase to the actual slab pouring stage, with a noticeable increase in work pace and the presence of concrete pumps on-site.
Expected next milestones
Stripping the wooden formwork after the concrete has cured and beginning the preparation for the next floor's columns.