20%Overall▲ +14% · vs previous visit

Main video

Engineering Report

The current site visit shows significant progress in foundation works, transitioning from excavation and preparation to the installation of concrete footings, formwork, and reinforcement steel, bringing foundation completion to 80%.
Detected changes
Foundations95%

Execution of concrete footings, installation of wooden formwork, and preparation of reinforcement steel for columns and ground beams.

Progress reading

The images reflect a 55% increase in foundation progress compared to the previous visit, as the site has moved from excavation to pouring footings and commencing formwork and steel reinforcement for ground beams and columns.

vs previous visit

During the previous visit, the site was in the excavation and preparation phase, whereas current images show significant progress in the concrete foundation structure, with concrete pumps and pouring equipment now on-site.

Expected next milestones

Complete the pouring of the remaining footings and ground beams, begin foundation waterproofing, and subsequently commence pouring the ground floor columns.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +14%
Foundations▲ +55%
0%
Concrete Works
0%
Finishing Works
0%
Electromechanical
0%

Drone Photography

Ground Photography

3D Model