12 Nov 2026
Main video
Engineering Report
Detected changes
Concrete pouring has been completed for the majority of the site, with only limited sections remaining in the preparation or pouring phase.
Significant progress in concrete pouring compared to the previous visit, which was limited to preparing formwork for columns and foundations.
Progress reading
The images reflect tangible progress in concrete and foundation works, as the site has shifted from intensive carpentry and steel fixing to ready-mix concrete pouring, accounting for the increase in completion rates (2% for foundations and 3% for concrete works).
vs previous visit
During the previous site visit, the project relied entirely on wooden formwork and rebar preparation for columns and foundations. In the current visit, concrete has been poured across most of the site, transforming the visual landscape from wooden structures into solid concrete surfaces.
Expected next milestones
Completion of the remaining foundation pours, removal of column formwork, and commencement of slab rebar preparation.