3 Oct 2026
3 Oct 2026
0%OverallFirst visit — no previous comparison.
Main video
Engineering Report
The site was visited on 2026-10-03, where concrete pouring for the foundations is currently underway using stationary concrete pumps. The project is in the initial foundation stage.
Detected changes
Concrete Structure95%
Commenced concrete pouring for the foundations, while continuing reinforcement steel works in the remaining sections and preparing the formwork.
Progress reading
The project is in its actual early stages (0% total completion), having transitioned from site preparation to the actual pouring of concrete foundations.
vs previous visit
Compared to the previous site visit (2026-09-22), significant progress is evident with the commencement of concrete pouring for the footings, whereas the previous visit was limited to preparation and steel reinforcement works.
Expected next milestones
Completion of all footing concrete pours, commencement of footing waterproofing, followed by the start of ground floor column installation.