22 Sept 2026
22 Sept 2026
0%OverallFirst visit — no previous comparison.
Main video
Engineering Report
The Al-Rawda project site was visited on 2026-09-22, where the site is currently in the preparation phase for foundation works (raft foundation). Ongoing activities are focused on floor reinforcement and the preparation of formwork for ground beams, with labor present on-site.
Detected changes
Concrete Structure (Foundations)95%
The installation of reinforcement steel for the raft foundation is complete, and the formwork for the ground beams is being prepared, with ongoing tying and final preparations for the concrete pour.
Site Overview90%
The site is fully fenced, with construction materials (reinforcement steel, wooden panels) distributed across the area, and workers are performing final preparations ahead of the concrete pour.
Progress reading
The project is in the foundation stage (0% total completion), with the images reflecting steel fixing and foundation reinforcement works preceding the reinforced concrete pouring process.
vs previous visit
No previous visit for comparison
Expected next milestones
Pouring of the foundation (raft) concrete following the approval of the ground beam reinforcement and steel works.